        | Our Future Home - Steeldust Meadows | 
         
                                                          
         
     | 
    
     
     | 
     
                                                            
     
                      
    These are pictures from July 2009. Now that the excavation has been dug, we spend the month setting
        up forms for the footings.  It's a pretty complicated foundation so is going to take a while.  We also get a load 
        of rebar.
     
     
    
     
    
    
    
    July 1st, 2009 - Now that we have a foundation permit we also get an address from 
        Rockyview County.
     
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 3rd, 2009 - We get a delivery of rebar and continue placing forms.
     
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 5th, 2009 - Rebar gets layed in the pit.
     
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 8th, 2009 - Drillers are in to drill our GeoThermal wells.
     
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
   
    
    
    
    July 10th, 2009 - Drillers finish up the GeoThermal wells.
     
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 12th, 2009 - Tracy helps with the footings and we get the outside done.
     
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 14th, 2009 - Inside forms for Jack Posts get layed out.
     
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 15th, 2009 - All the Jack Posts are layed out and we start on the inside of 
        the footing forms.  The GeoThermal guys are done and we have 6 pipe loops sticking out of the ground.  They each 
        go down 68m.
     
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 16th, 2009 - Putting the boxes together for the Jack Posts.
     
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 20th, 2009 - We have a visitor.  A local fox shows up for a drink.
     
     
    
     
    
     
    
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 27th, 2009 - More work on footings.
     
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    July 31st, 2009 - More work on the inside forms for footings.
     
     
    
     
    
     
    
     
     | 
     
     
     
    
    
    
    
    June, 2009
     
    May, 2009
     
    April, 2009
     
    March, 2009
     
    February, 2009
     
    January, 2009
     
    December, 2008
     
    November, 2008
     
    October, 2008
     
    September, 2008
     
    August, 2008
     
    July, 2008
     
    June, 2008
     
    May, 2008
     
    April, 2008
     
    March, 2008
     
    February, 2008
     
    January, 2008
     
    December, 2007
     
    November, 2007
     
    October, 2007
     
    September, 2007
     
    August, 2007
     
    July, 2007
     
    June, 2007
     
    May, 2007
     
    April, 2007
     
    March, 2007
     
    February, 2007
     
    January, 2007
     
    December, 2006
     
    November, 2006
     
    October, 2006
     
    September, 2006
     | 
                          
     
 |